Generators · Transfer Switches · UPS · Emergency Power
When the Utility Drops, Your Building Doesn’t.
Standby generators, automatic transfer switches and UPS systems, installed, connected and tested for facilities where an outage costs real money or puts people at risk.
Generators, ATS & UPS
Backup Power Only Counts If It Transfers.
A generator that has never been load tested, or a transfer switch wired to the wrong loads, is a false sense of security. Emergency, legally required and optional standby systems each carry their own code requirements, and healthcare and mission-critical facilities add transfer time and redundancy on top.
We install the complete backup power path: generator set and connections, fuel and exhaust coordination with the mechanical trades, transfer switches, UPS and batteries, and the distribution they feed. Then we test it with the owner watching, so everyone knows it works before the day it has to.
Scope
What We Install
- 01
Standby generators
Setting, connecting and commissioning diesel and natural gas generator sets.
- 02
Automatic transfer switches
ATS installation, including load separation for emergency, legally required and optional standby branches.
- 03
Paralleling gear
Paralleling switchgear for multi-generator systems and redundancy.
- 04
UPS systems
UPS installation, battery systems and bypass arrangements for critical loads.
- 05
Generator connections
Docking stations and quick-connect cabinets for portable generators.
- 06
Load testing
Startup, load bank testing and witnessed transfer tests at closeout.
Why Anvil Edge
Why Owners Trust Us With It
- 01
Healthcare experience
Our leadership has run essential electrical systems on VA hospitals and medical facilities.
- 02
Mission-critical mindset
Redundancy and transfer paths planned so single points of failure are designed out.
- 03
Code-driven separation
NEC 700, 701 and 702 systems kept separate as the code requires.
- 04
Tested, not assumed
Every system is load tested and transfer tested before turnover.
Process
From Sizing to Witnessed Test.
- 1
Loads & Sizing
Critical loads identified and coordinated with the engineer of record.
- 2
Equipment Release
Generator, ATS and UPS submittals and lead times locked in.
- 3
Install & Connect
Pads, conduit, feeders and control wiring installed.
- 4
Startup
Manufacturer startup and system checks.
- 5
Load & Transfer Test
Load bank and transfer testing with the owner present.
FAQ
Common questions.
What is the difference between emergency and standby power?
Emergency systems (NEC 700) power life safety loads like egress lighting and must transfer within 10 seconds. Legally required standby (NEC 701) and optional standby (NEC 702) serve other loads with less strict requirements. Each has to be kept separate as the code requires.
Do you install UPS systems as well as generators?
Yes. For data rooms and critical equipment we install the UPS and batteries to carry the load through the transfer, and the generator to carry it after.
Can you add a generator to an existing building?
Yes. We assess the existing service and distribution, separate the loads to be backed up, and plan the tie-in with a short scheduled shutdown.
Industries we do this for
Start a project
Planning Backup Power?
Tell us what has to stay on and for how long. We will scope the generator, transfer and UPS side.
- 110 S Jefferson Rd, Whippany, NJ 07981
